An £8.6 million steel frame, 3 storey new building on the sited on the town hall car park.

A government funded college that offers 14 – 18 year olds an innovative learning environment in bio medical sciences and design engineering.

Works Performed

  • Site strip, foundations, pads and waste removal.
  • Foul and storm drainage.
  • Triton attenuation system.
  • Ground floor slab – Rebar, formwork, concrete.
  • Concrete to upper composite metal flooring.
  • External works – hard landscaping.
  • 5M deep volclay water proofing to old existing building requiring deep valclay wtaer proofing to old existing building requiring temporary works shoring system
  • Part of the site was contaminated with asbestos which was isolated by a specialist contractor.
  • GECON disposed of soil in that area by using a specialist hauler to a registered tip for treatment.