Project Brief
A new £9 million special needs school close to Daventry Town Centre on a green field site forming part of Daventry District Councils Learning Quarter plan.
The site is on a steep incline requiring Larsen sheet piles retaining the higher level.
Works Performed
- Cut and fill split level foundations & pads for stanchions
- Waste disposal
- Drainage including 250m of 300mm wrapped
- Perforated land drain and 400m2 triton attenuation tank
- Rebar, formwork and concrete to ground floor slabs
- Service excavations
- Hydrotherapy pool
- Car park
- Edgings, kerbing and slabbing.